Al Dibdibah Power and Al Shagaya Renewable Energy, phase III zone 1

A 1,100 MW solar PV project at Shagaya Renewable Energy Park, Al Jahra, Kuwait. Stage: Tendered.

The record

What the sources publish for this project

Capacity
1,100 MW
Technology
Solar PV
Stage counted on this site
TenderedAs published: “Technical evaluation complete; financial bids to be opened” (Zawya)
Tender
June 2025
Owners and developers
No owner or developer is named in a public source yet
Supplies
Ministry of Electricity, Water and Renewable Energy
Procurer
KAPP and the Ministry of Electricity, Water and Renewable Energy
Arrangement
Independent power project with a power purchase agreementTerm: 30 years
Country
Kuwait
Location
Shagaya Renewable Energy Park, Al Jahra, KuwaitLocality and region only; plant coordinates are not published

The request for proposals went to six prequalified bidders in June 2025, with a 30-year power purchase agreement with the ministry from the commercial operation date.

Modelled output

Estimated annual generation

Modelled, not measured

2,186

GWh a year

22.7%

Capacity factor

25.5% of the modelled output of this tracker’s tendered solar projects.

  • Fixed at the optimal tilt1,876 GWh19.5%1,706 kWh per kWp
  • Single-axis trackerCounted here2,186 GWh22.7%1,987 kWh per kWp

Yield read at the centre of Al Jahra Governorate: the tracker names no town this model can place. Mounting assumed: plants of 50 MW and more on single-axis trackers, smaller ones fixed.

Annual kWh per kWp from PVGIS for crystalline silicon with 14% system loss, multiplied by the capacity as the source states it and taken as peak. A plant rated in MWac carries more DC capacity, so its estimate runs low.

Tracker totals, modelled

Solar projects with an estimate only; the counted mounting for each.
StageProjectsCapacity, MWGWh a yearCapacity factor
Operational11 / 127,57515,70923.7%
Under construction5 / 510,10021,17123.9%
Contracted2 / 22,5005,18123.7%
Tendered5 / 54,2008,55923.3%
Announced1 / 11,5003,15524%

Solar yield: PVGIS 5.2 (PVGIS-SARAH2), European Commission, Joint Research Centre. © European Union. Estimate as JSON

Sources

Where each figure comes from

PublisherPublicationPublishedRead onKind
pv magazineKuwait reveals prequalified bidders for 1.1 GW solar project16 June 202524 September 2026Press or compiler
ZawyaKuwait set to open financial bids for 1.1GW Shagaya solar PV projectUndated24 September 2026Press or compiler

Solar and wind resource

The resource at Al Jahra

NASA POWER's long-run means for the 0.5° cell that holds the locality: an area-level picture, not a site measurement.

5.70 kWh/m²/day

Global horizontal irradiance

About 2,081 kWh/m² a year

4.82 kWh/m²/day

Direct normal irradiance

6.5 m/s

Wind at 50 m

26.0 °C

Air temperature

Warmest month July, 38.3 °C

Aerosol optical depth: 0.50 · Dustiest month May

Global horizontal irradiance by month, kWh/m²/day
January: 3.54 kWh/m²/dayJanFebruary: 4.46 kWh/m²/dayFebMarch: 5.62 kWh/m²/dayMarApril: 6.24 kWh/m²/dayAprMay: 7.12 kWh/m²/dayMayJune: 8.00 kWh/m²/dayJunJuly: 7.68 kWh/m²/dayJulAugust: 7.24 kWh/m²/dayAugSeptember: 6.40 kWh/m²/daySepOctober: 5.02 kWh/m²/dayOctNovember: 3.74 kWh/m²/dayNovDecember: 3.28 kWh/m²/dayDec
January3.54
February4.46
March5.62
April6.24
May7.12
June8.00
July7.68
August7.24
September6.40
October5.02
November3.74
December3.28

Source: NASA Langley Research Center POWER Project, climatology 2001–2020, public domain; retrieved 2026-09-24. Cell N29.5E47.0, native resolution 1° (CERES SYN1deg). These data were obtained from the NASA Langley Research Center (LaRC) POWER Project funded through the NASA Earth Science/Applied Science Program.

See it on the Energy AtlasResource as JSON