GCC Renewables Tracker

36 utility-scale solar, wind and battery projects across the United Arab Emirates, Oman, Qatar, Kuwait and Bahrain, adding up to 27.9 GW of capacity as each source states it. Every row names the publications it was taken from.

  • Source DEWA, EWEC, Nama PWP, KAHRAMAA and QatarEnergy, KAPP and the Ministry of Electricity, Water and Renewable Energy, KISR and EWA, with developer releases and trade press where the procurer does not publish
  • Licence Compiled from public sources; each row links the publication it was taken from
  • Compiled 24 September 2026, edition 2026-09

36

Projects tracked

Five countries

Source: GCC Renewables Tracker, compiled 24 September 2026; MW as each source states it

8,929 MW

Operating

17 projects

Source: GCC Renewables Tracker, compiled 24 September 2026; MW as each source states it

10,100 MW

Under construction

5 projects

Source: GCC Renewables Tracker, compiled 24 September 2026; MW as each source states it

8,845 MW

Contracted, tendered or announced

14 projects

Source: GCC Renewables Tracker, compiled 24 September 2026; MW as each source states it

By country

Capacity by country and stage

Megawatts are added as each source states them: MWac for most procurers, MWp where the developer publishes only the direct-current size. Battery energy in MWh is never added. A project with no published capacity is counted in the project column only.

CountryProjectsMWOperating MWUnder construction MWContracted MWTendered MWAnnounced MW
United Arab Emirates1519,4545,55410,000—2,0001,900
Oman122,8951,650—745500—
Qatar43,6751,675—2,000——
Kuwait31,65050——1,600—
Bahrain2200—100—100—
Five countries3627,8748,92910,1002,7454,2001,900

Projects with no single published capacity yet: 3. They are counted as projects and left out of the MW columns.

By stage

Capacity by stage

StageProjectsMW
Operating178,929
Under construction510,100
Contracted42,745
Tendered84,200
Announced21,900

GCC Renewables Tracker, compiled 24 September 2026; MW as each source states it

Projects

Every project, with its source

36 of 36

Country

Technology

Stage

GCC utility-scale renewable projects. Capacity as the source states it; the date is the commercial operation date, the inauguration, or the stated target where marked expected.
ProjectCountryTechnologyCapacityStageOwners and developersOperation datePublished tariff
Mohammed bin Rashid Al Maktoum Solar Park, phase 2United Arab EmiratesSolar PV200 MWOperatingACWA Power, TSK20 March 20175.6 US cents/kWh (USD) · Mohammed bin Rashid Al Maktoum Solar Park Innovation Centre (DEWA)
Mohammed bin Rashid Al Maktoum Solar Park, phase 3United Arab EmiratesSolar PV800 MWOperatingMasdar20202.99 US cents/kWh (USD) · Mohammed bin Rashid Al Maktoum Solar Park Innovation Centre (DEWA)
Mohammed bin Rashid Al Maktoum Solar Park, phase 4 (Noor Energy 1)United Arab EmiratesConcentrated solar and PV950 MWOperatingDEWA, ACWA Power, Silk Road FundQ1 20247.3 US cents/kWh (USD) · ACWA Power
Mohammed bin Rashid Al Maktoum Solar Park, phase 5United Arab EmiratesSolar PV900 MWOperatingDEWA, ACWA Power, Gulf Investment CorporationJune 20231.6953 US cents/kWh (USD) · Mohammed bin Rashid Al Maktoum Solar Park Innovation Centre (DEWA)
Mohammed bin Rashid Al Maktoum Solar Park, phase 6United Arab EmiratesSolar PV1,800 MWUnder constructionDEWA, Masdar2026, expected1.6215 US cents/kWh (USD) · Masdar
Mohammed bin Rashid Al Maktoum Solar Park, phase 7United Arab EmiratesSolar PV and battery2,000 MWTendered———
Noor Abu DhabiUnited Arab EmiratesSolar PV1,000 MWacOperatingTAQA, Marubeni, Jinko PowerApril 20198.888 fils/kWh (AED) · EWEC
Al Dhafra Solar PVUnited Arab EmiratesSolar PV1,500 MWacOperatingTAQA, Masdar, EDF Renewables, Jinko PowerNovember 20234.85 fils/kWh (AED) · EWEC
Al Ajban Solar PVUnited Arab EmiratesSolar PV1,500 MWUnder constructionMasdar, EDF Renewables, KOWEPOQ3 2026, expected5.1921 fils/kWh (AED) · REVE (evwind)
Khazna Solar PVUnited Arab EmiratesSolar PV1,500 MWacUnder constructionENGIE, Masdar——
Zarraf Solar PVUnited Arab EmiratesSolar PV1,500 MWacAnnounced———
Round-the-clock solar and storage project, Abu DhabiUnited Arab EmiratesSolar PV and battery5,200 MWpUnder constructionMasdar2027, expected—
Wahat Al Zaweya BESSUnited Arab EmiratesBattery storage400 MWAnnounced———
Shams 1United Arab EmiratesConcentrated solar100 MWOperatingMasdar, TotalEnergies, AbengoaMarch 2013—
UAE Wind ProgramUnited Arab EmiratesOnshore wind103.5 MWOperatingMasdar5 October 2023—
Ibri II Solar IPPOmanSolar PV500 MWacOperatingACWA Power, Gulf Investment Corporation, Alternative Energy Projects Co.6 August 2021—
Manah 1 Solar IPPOmanSolar PV500 MWOperatingEDF Renewables, KOWEPO22 January 2025—
Manah II Solar IPPOmanSolar PV500 MWOperatingSembcorp, Jinko PowerDecember 2024—
Ibri III Solar IPPOmanSolar PV and battery500 MWContractedMasdar, OQ Alternative Energy, Al Khadra Partners, KOMIPO——
Amin Solar IPPOmanSolar PV100 MWOperatingMarubeni, Oman Gas Company, Bahwan Renewable Energy, Nebras PowerJune 2020—
Dhofar Wind IOmanOnshore wind50 MWOperatingMasdarNovember 2019—
Dhofar Wind II IPPOmanOnshore wind125 MWContractedSembcorp, OQ Alternative EnergyQ3 2027, expected—
Jaalan Bani Bu Ali Wind IPPOmanOnshore wind120 MWContractedEDF Renewables, Al Khadra Partners, OQ Alternative EnergyQ3 2027, expected—
Al Kamil I Solar IPPOmanSolar PV500 MWTendered—Q2 2027, expected—
Duqm Wind IPP (Ras Madrakah)OmanOnshore windNot publishedTendered—Q4 2027, expected—
Mahoot Wind I IPPOmanOnshore windNot publishedTendered—Q4 2027, expected—
Sadah Wind IPPOmanOnshore windNot publishedTendered—Q4 2027, expected—
Al Kharsaah Solar PVQatarSolar PV800 MWpOperatingQatarEnergy Renewable Solutions, TotalEnergies, Marubeni18 October 2022—
Mesaieed Solar PVQatarSolar PV417 MWOperatingQatarEnergy28 April 2025—
Ras Laffan Solar PVQatarSolar PV458 MWOperatingQatarEnergy28 April 2025—
Dukhan Solar PVQatarSolar PV2,000 MWContractedQatarEnergy2029, expected—
Shagaya CSP (phase 1)KuwaitConcentrated solar50 MWOperatingKISRDecember 2018—
Al Dibdibah Power and Al Shagaya Renewable Energy, phase III zone 1KuwaitSolar PV1,100 MWTendered———
Al Dibdibah Power and Al Shagaya Renewable Energy, phase III zone 2KuwaitSolar PV500 MWTendered———
Al Dur Solar PVBahrainSolar PV100 MWUnder constructionEWAQ3 2026, expected—
Bilaj Al Jazayer Solar IPPBahrainSolar PV100 MWTendered—Q3 2027, expected—

How it is compiled

Sources first, one row at a time

Projects of 50 MW or more that use solar PV, concentrated solar, wind or batteries, from the tender stage to operation. Saudi Arabia is covered by the Saudi Renewables Tracker.

Each row is taken from the procurer's own pages where they publish (DEWA, EWEC, Nama PWP, KAHRAMAA and QatarEnergy, KAPP, EWA), from the developer's release where they do not, and from trade press only where neither does. Every source is listed on the project's page with the date it was read.

Where two sources give different figures, both are kept on the project's page and the page says which one this site counts and why. A figure no source publishes is left empty rather than estimated.

A tariff is shown only where the procurer or the developer published one, in the currency and unit published. Bid prices in a tender that has not been awarded are not shown.

There is no plant map. This tracker publishes each project's country and locality in text; plant coordinates are not published.