Project
HUMAIN-AMD-Cisco AI infrastructure
HUMAIN-AMD-Cisco AI infrastructure: AI and data centres, Operational, in Saudi Arabia.
What the source says
HUMAIN-AMD-Cisco AI infrastructure
Production systems live per the August 2026 release; next phase up to 250 MW with first capacity expected in the second half of 2027; program up to 1 GW by 2030. Operating MW and site are not disclosed. Reviewed against operator and partner primary releases, 12 September 2026.
Source: Saudi Data Centre Load Tracker, as compiled on September 2026.
Classification
This project on the site's facets
The same fields every project in the index carries. Not disclosed means the source publishes nothing for it; nothing is estimated.
- Place
- Saudi ArabiaRolls up to: GCC · MENA · Arab League · OPEC · OPEC+ (Declaration of Cooperation)
- Sector
- AI and data centres
- Technology
- AI data centres
- Stage
- OperationalIn the source's words: operational
- Announced
- Pre-feasibility
- Feasibility
- Front-end engineering design (FEED)
- Permitting
- Procurement
- Awarded
- Offtake signed
- Final investment decision
- Financial close
- Construction
- Commissioning
- Operational
- Expansion
- Decommissioned
- On hold, delayed or cancelled
- Not disclosed
- Commitment
- Not disclosed
- Reported
- Announced intent
- Memorandum or framework
- Joint development agreement or heads of agreement
- Contract (PPA, EPC or offtake)
- Final investment decision
- Financial close
- Programme
- Not disclosed
- Investment
- $10bn
- Capacity
- Not disclosedOperating MW undisclosed; 1 GW is the 2030 program target
- Annual output
- Not disclosed
- Tariff or levelised cost
- Not disclosed
- Emissions
- Not disclosed
Milestones
| Milestone | Date | Planned or actual |
|---|---|---|
| Commercial operation date (COD) | 2026 | Actual |
Companies and bodies
- HUMAINDeveloper
- AMDDeveloper
- CiscoDeveloper
Where it comes from
- Dataset
- Saudi Data Centre Load Tracker
- Source type
- Company release
- Verification
- Not disclosed
- Last updated
- September 2026