Company
ACWA Power
ACWA Power is named as a developer or shareholder on 23 projects in the Saudi Renewables Tracker, 34,716 MW in total.
9,016 MW
Operating
9 projects
Source: Saudi Renewables Tracker, stage per the Principal Buyer register, 12 September 2026
21,200 MW
Under construction
11 projects
Source: Saudi Renewables Tracker, stage per the Principal Buyer register, 12 September 2026
4,500 MW
Tendered
3 projects
Source: Saudi Renewables Tracker, stage per the Principal Buyer register, 12 September 2026
3,667 MW
Attributable by published equity share
Projects that publish a share: 9 of 23; the others are not counted
Source: Saudi Renewables Tracker, stage per the Principal Buyer register, 12 September 2026
Portfolio
Projects that name this company
Capacity is the whole project’s; the share is the equity the developers publish.
| Project | MW | Share | Attributable MW | Technology | Stage | Year |
|---|---|---|---|---|---|---|
| Al Humaij | 3,000 | Not published | — | Solar PV | Under construction | 2028 |
| Bisha | 3,000 | Not published | — | Solar PV | Under construction | 2028 |
| Shuaibah 2 | 2,060 | 35.01% | 721 | Solar PV | Operating | 2024 |
| Afif 1 | 2,000 | Not published | — | Solar PV | Under construction | 2028 |
| Afif 2 | 2,000 | Not published | — | Solar PV | Under construction | 2028 |
| Ar Rass 2 | 2,000 | 40.01% | 800 | Solar PV | Operating | 2025 |
| Haden | 2,000 | Not published | — | Solar PV | Under construction | 2026 |
| Haden 2 | 2,000 | Not published | — | Solar PV | Tendered | 2029 |
| Khulis | 2,000 | Not published | — | Solar PV | Under construction | 2028 |
| Muwayh | 2,000 | Not published | — | Solar PV | Under construction | 2026 |
| Muwayh 2 | 2,000 | Not published | — | Solar PV | Tendered | 2029 |
| Starah | 2,000 | Not published | — | Onshore wind | Under construction | 2028 |
| Khushaybi | 1,500 | Not published | — | Solar PV | Under construction | 2027 |
| Sudair | 1,500 | 35% | 525 | Solar PV | Operating | 2023 |
| Kahfah | 1,425 | 50.1% | 714 | Solar PV | Operating | 2025 |
| Shaqra | 1,000 | Not published | — | Onshore wind | Under construction | 2028 |
| Ar Rass 1 | 700 | 40.01% | 280 | Solar PV | Operating | 2024 |
| Yunbu | 700 | Not published | — | Onshore wind | Under construction | 2027 |
| Shuaibah 1 | 600 | 35.01% | 210 | Solar PV | Operating | 2024 |
| Khushaybi 2 | 500 | Not published | — | Solar PV | Tendered | 2029 |
| Red Sea Project | 340 | 50% | 170 | Solar PV | Operating | 2026 |
| Sakaka | 300 | 70% | 210 | Solar PV | Operating | 2020 |
| Layla | 91 | 40% | 36 | Solar PV | Operating | 2024 |
Technology mix
Capacity by technology
| Technology | Projects | MW | Share of portfolio MW |
|---|---|---|---|
| Solar PV | 20 | 31,016 | 89.3% |
| Onshore wind | 3 | 3,700 | 10.7% |
What changed
Recent changes across its projects
| Date | Project | Change | Before and after | Source |
|---|---|---|---|---|
| 2026-09-12 | Khushaybi | Added to the register (backfilled) | — → 1,500 MW | Principal Buyer register |
| 2026-09-12 | Al Humaij | Added to the register (backfilled) | — → 3,000 MW | Principal Buyer register |
| 2026-09-12 | Muwayh | Added to the register (backfilled) | — → 2,000 MW | Principal Buyer register |
| 2026-09-12 | Haden | Added to the register (backfilled) | — → 2,000 MW | Principal Buyer register |
| 2026-09-12 | Sakaka | Added to the register (backfilled) | — → 300 MW | Principal Buyer register |
| 2026-09-12 | Sudair | Added to the register (backfilled) | — → 1,500 MW | Principal Buyer register |
| 2026-09-12 | Shuaibah 1 | Added to the register (backfilled) | — → 600 MW | Principal Buyer register |
| 2026-09-12 | Ar Rass 2 | Added to the register (backfilled) | — → 2,000 MW | Principal Buyer register |
| 2026-09-12 | Kahfah | Added to the register (backfilled) | — → 1,425 MW | Principal Buyer register |
| 2026-09-12 | Shuaibah 2 | Added to the register (backfilled) | — → 2,060 MW | Principal Buyer register |
| 2026-09-12 | Bisha | Added to the register (backfilled) | — → 3,000 MW | Principal Buyer register |
| 2026-09-12 | Afif 1 | Added to the register (backfilled) | — → 2,000 MW | Principal Buyer register |
| 2026-09-12 | Yunbu | Added to the register (backfilled) | — → 700 MW | Principal Buyer register |
| 2026-09-12 | Starah | Added to the register (backfilled) | — → 2,000 MW | Principal Buyer register |
| 2026-09-12 | Shaqra | Added to the register (backfilled) | — → 1,000 MW | Principal Buyer register |
| 2026-09-12 | Khulis | Added to the register (backfilled) | — → 2,000 MW | Principal Buyer register |
| 2026-09-12 | Afif 2 | Added to the register (backfilled) | — → 2,000 MW | Principal Buyer register |
| 2026-09-12 | Layla | Added to the register (backfilled) | — → 91 MW | Principal Buyer register |
| 2026-09-12 | Ar Rass 1 | Added to the register (backfilled) | — → 700 MW | Principal Buyer register |