Saudi Renewables Tracker
Tabarjal solar PV project
A 400 MW solar PV project at Tubarjal, Al-Jawf, under construction according to the Principal Buyer register.
The record
What the tracker and the register hold for this project
- Capacity
- 400 MWSaudi Renewables Tracker, KAPSARC snapshot 12 September 2026
- Technology
- Solar PV
- Stage counted on this site
- Under constructionTaken from the Principal Buyer register, checked 21 September 2026; the register leads where it and the tracker disagree
- Stage in the Principal Buyer register
- Under constructionListed as “Tabarjal”; Saudi Power Procurement Company, checked 21 September 2026
- Stage as the tracker’s source publishes it
- InstalledKAPSARC Renewable Energy Projects Dashboard, snapshot 12 September 2026 The Principal Buyer register records a different stage. This site counts the register’s stage, because the Principal Buyer contracts the power and signs off commercial operation; the tracker’s reading stays published here.
- Completion year
- 2026As published; a year still ahead is a stated target
- Procurement route
- National Renewable Energy Program, round 4
- Tender year
- 2022
- Developers and published equity shares
- Shares as the developers publish them; a company without a share has not published one
- Grid
- National grid project
- Location
- Tubarjal, Al-JawfLocality and region only; plant coordinates are not published
- Levelised cost of electricity, as tendered
- 1.708 US cents per kWhAs published in the KAPSARC dashboard, snapshot 12 September 2026
- Annual generation, modelled
- 840,960 MWh a yearModelled in the tracker as capacity × 8,760 hours × a 24% capacity factor. Not metered output.
KAPSARC, Renewable Energy Projects Dashboard (July 2026 project data, snapshot 12 September 2026); SPPC / Principal Buyer, Renewable project register (38 records checked 11 September 2026). Tracker edition 2026-Q3.
Projects you watch are listed on your account page.
What changed
Changes on record for this project
Each entry is a change a weekly sync observed in the Principal Buyer register or the tracker, with the value on both sides.
| Date | Change | Before and after | Source |
|---|---|---|---|
| 2026-09-12 | Added to the register (backfilled) | — → 400 MW | Principal Buyer register |
Location
Tubarjal, Al-Jawf
The tracker places this project at Tubarjal, in Al-Jawf. This site publishes locality and region only: plant coordinates are confidential and are not shown on this page, in its data or in its API.