Covers the Saudi battery fleet and the projects behind it: what is energised, what is awarded, what sits in the two Principal Buyer procurement groups, and the dedicated systems at The Red Sea, AMAALA and NEOM Green Hydrogen. The combined project ledger is 44.3 GWh — 42 GWh of grid projects, of which 18 GWh was energised by the end of June 2026, plus about 2.3 GWh of dedicated systems — which the report states spans different delivery stages and is not an operating-fleet total. It also keeps battery capital cost apart from the cost of discharged energy. Figures are as compiled on 12 September 2026.
- Compiled 12 September 2026
- 6 pages

What the report covers
Saudi Arabia's battery story now spans operating assets, signed agreements and a growing procurement pipeline.
Saudi Energy reported 18 GWh energized by the end of June 2026. The grid-project ledger adds 4 GWh of further awarded projects, 8 GWh under SPPC's first-group agreements and 12 GWh in second-group procurement.
Together, these represent 42 GWh of grid projects. Dedicated systems at The Red Sea, AMAALA and NEOM Green Hydrogen add approximately 2.3 GWh, bringing the combined project ledger to 44.3 GWh. The total includes different delivery stages; it is not an operating-fleet total.
This carousel maps the fleet, identifies the procurement groups and separates battery capital costs from the cost of discharged energy.
For the next wave, project value will depend on location, duration, operating constraints and the service being procured.
Which of those will matter most as the fleet grows?
Source/system ratings are retained. The dedicated total uses AMAALA's 700 MWh basis; the alternative 770 MWh report describes the same asset.
What the figures mean
Quoted from the report's own notes on scope and definitions, in the words it published them in.
- 70 GW renewable project coverage: rounded from 63.813 GW in the grid-project register + 4.49 GW across NGHC, The Red Sea and AMAALA + 2 GW of separately reported ENOWA tenders. This combines different project stages and source AC/DC conventions; it is not operating capacity or a new official national total. The two ENOWA reports date to July 2024; current awards and final grid interfaces are unverified.
- 44.3 GWh battery projects: 18 GWh energized grid capacity + 4 GWh of further Saudi Energy awarded projects + 8 GWh under SPPC Group 1 agreements + 12 GWh of Group 2 procurement + 2.327 GWh in dedicated systems = 44.327 GWh. It is not an all-operating fleet total. Power in GW and energy in GWh are separate quantities.
- Dedicated battery ratings: Red Sea 1.227 GWh + AMAALA 0.700 GWh + NGHC 0.400 GWh. EDF's 0.770 GWh AMAALA figure and Sungrow's 0.600 GWh DC NGHC quantity have different reporting bases and are not additional projects.
- LCOE map coverage: all 41 registered solar projects (51.613 GW) and 12 wind projects (12.200 GW) are represented. Hollow markers show 10 solar and five wind projects without published prices. This is the full grid-project register; dedicated off-grid projects are covered in the separate dedicated-systems PDF.
- Renewable price averages: sum of project capacity multiplied by its reported price, divided by total priced capacity. Solar: 31 priced projects, 36.513 GW, approximately 1.47 US cents/kWh. Wind: seven priced projects, 6.700 GW, approximately 1.77 US cents/kWh. Unpriced projects are excluded from the averages but remain on the maps. These are capacity-weighted means, not medians or generation-weighted averages; reported contract vintages are retained.
- Battery costs: the approximately USD 120/kWh and USD 123/kWh Tabuk and Hail figures are capital-cost comparisons using the cited procurement energy basis. The 6.5 US cents/kWh storage benchmark is an Ember modeled LCOS excluding charging energy, not a Saudi auction discharge tariff.
- Locations: points are project or named-area proxies where surveyed plant coordinates are unavailable. The ENOWA tender locations are indicative named areas. They do not establish final engineering footprints.
Sources
The PDF carries its own source page as well.
- Saudi Energy
- SPPC / Principal Buyer
- Saudi Press Agency / SPPC
- SPPC / Principal Buyer
- Ember
- KAPSARC — Renewable Energy Projects Dashboard
- SPPC / Principal Buyer — Renewable project register
- SPPC / Principal Buyer — Round 7: six projects, 5,300 MW
- SPPC / Principal Buyer — Round 7 qualified developers
- SPPC / Principal Buyer — Round 6 awards and exact LCOEs
- SPPC / Principal Buyer — Seven PPAs totaling 15,000 MW
- Saudi Energy — H1 2025 results presentation, p. 8
- NR Electric — 2.5 GW storage cluster energized
- HiTHIUM — Tabuk and Hail: 4 GWh contract
- geoBoundaries / © OSM contributors — Saudi province map data
- Acwa — The Red Sea: commercial operation
- Red Sea Global — AMAALA utility concession
- Masdar — Green Finance Report 2024, p. 14
- EDF — 2025 registration document, p. 84
- Acwa — NEOM Green Hydrogen project
- NEOM Green Hydrogen Co. — Project progress and milestones
- Tecnicas Reunidas — Yanbu hydrogen FEED award
- Larsen & Toubro — Yanbu renewables and grid scope
- GlassPoint — Maaden Solar I project
- MEED — ENOWA Gayal and Shiqri tenders
- NEOM — Official supplier portal
- Etimad — Al Khafji solar technical support
- Royal Commission for AlUla — Official supplier portal
- Italian Trade Agency / MEED — Round 7 deadline reporting
- Sungrow — NGHC inverter and battery contract
- NEOM Green Hydrogen Co. — Battery system: 400 MW / 400 MWh
- IRENA — Renewable capacity statistics 2026
- IEA — COP28 capacity pledge: 2025 update
- KAPSARC — Dashboard project coordinates and unrounded prices
- Maaden — Solar steam showcase at Ras Al Khair alumina refinery
- Aramco — Renewables not that new
- Aramco — First wind turbine at Turaif Bulk Plant
- Bundesnetzagentur — Onshore wind auction statistics
- Bundesnetzagentur — Ground-mounted solar auction statistics
- UK Department for Energy Security and Net Zero — Allocation Round 7 completed results
- China NDRC / NEA — Renewable electricity pricing reform, Notice 136
- Global Energy Monitor — Solar and wind project location records
- GeoNames — Geographic place gazetteer
- Electronics / MDPI — A Case Study of a Stand-Alone AC and DC Power Network in the Red Sea New City
- DistancesFrom — Al Midra Tower coordinates
- The Wind Power — Turaif oil storage depot wind turbine
- Saudi Energy / Saudi Exchange — Al-Muwaih storage services agreement
- Saudi Energy / Saudi Exchange — Haden storage services agreement
- Saudi Energy / Saudi Exchange — Kahafah storage services agreement
- SaudiGulf Projects — SEC receives bids for 1,000 MW battery storage
- Windy.app — Gayal named-area location reference
Preview
3 of 6 pages shown



Get the report
Saudi battery storage
Get the PDF free with membership
The PDF and the data files are free for members. Membership takes a minute: verify an email address or a mobile number once, and the download opens along with the dashboards and CSV export.
Create a free account and the download starts as soon as you are in. You come back to this report.
Not ready to join?
Weekly update
Saudi renewables, weekly: stage changes, tenders and commercial operation dates. One email on Sunday.
By continuing with one of these accounts, you accept the terms of use, including the licence and the member terms, and the privacy policy.
We use your details to provide access and, if you opt in, to send you the weekly brief or the alerts you choose. Privacy policy
Figures are as filed on 12 September 2026; live dashboards may differ. Open the live dashboard