Saudi renewables: what comes next
3 projects are yet to operate, 5.1 GW in all: 3.0 GW under construction and 2.1 GW awarded, in tender or announced.
- Projects
- 3
- Tracked capacity
- 5.1GW3 projects
- Under construction
- 3.0GW1 project
- Awarded, in tender or announced
- 2.1GW2 projects
Capacity due by year of operation
3.0 GW2027
2.1 GW2029
Years are the sources’ own commercial operation dates, planned or actual, and move. Projects without a date are left out.
Where it is being built
- Under construction
- Awarded, in tender or announced
Circle area shows capacity. Locations are locality points, indicative, not surveyed sites.
Capacity to come by province
- Aseer5.1 GW3 projects
Projects by year of operation
| Project | Capacity | Technology | Stage | Operation |
|---|---|---|---|---|
| Bisha | 3,000 MW | Solar photovoltaic | Construction | 2027 |
| Al Qirah | 1,500 MW | Wind | Procurement | 2029 |
| Tathleeth | 600 MW | Solar photovoltaic | Procurement | 2029 |