Saudi renewables: what comes next

41 projects are yet to operate, 56.2 GW in all: 33.6 GW under construction and 22.6 GW awarded, in tender or announced.

Projects
41
Tracked capacity
56.2GW41 projects
Under construction
33.6GW24 projects
Awarded, in tender or announced
22.6GW17 projects

Capacity due by year of operation

6.2 GW2026
24.2 GW2027
2.9 GW2028
20.6 GW2029

Years are the sources’ own commercial operation dates, planned or actual, and move. Projects without a date are left out.

Where it is being built

NGHC · 3,900 MWAl Humaij · 3,000 MWBisha · 3,000 MWAs Sdawi 2 · 3,000 MWAl-Leeth · 3,000 MWAfif 2 · 2,000 MWHaden · 2,000 MWMuwayh 2 · 2,000 MWAs Sdawi · 2,000 MWStarah · 2,000 MWKhulis · 2,000 MWMuwayh · 2,000 MWAfif 1 · 2,000 MWHaden 2 · 2,000 MWDwadmi · 1,500 MWHenakiyah 3 · 1,500 MWAl Qirah · 1,500 MWTabarjal 2 · 1,400 MWNajran · 1,400 MWBilghah · 1,300 MWGayal · 1,200 MWAl Masa'a · 1,000 MWShaqra · 1,000 MWBaeyda'a Nathel 1 · 1,000 MWShegran · 900 MWSamha · 800 MWShiqri · 800 MWYunbu · 700 MWAl Darb · 600 MWTathleeth · 600 MWMawqaq · 600 MWAlghat · 600 MWSamtah · 600 MWWaad Al Shammal · 500 MWSouth Ola · 500 MWKhushaybi 2 · 500 MWHenakiyah 2 · 400 MWSufun · 400 MWTabarjal · 400 MWRabigh 2 · 300 MWAmaala · 250 MW
  • Under construction
  • Awarded, in tender or announced

Circle area shows capacity. Locations are locality points, indicative, not surveyed sites.

Capacity to come by province

  • Makkah13.3 GW7 projects
  • Riyadh10.1 GW7 projects
  • Madinah8.3 GW7 projects
  • Aseer5.1 GW3 projects
  • Eastern Province5.0 GW2 projects
  • NEOM3.9 GW1 project
  • Hail2.0 GW3 projects
  • Tabuk2.0 GW2 projects

Projects by year of operation

ProjectCapacityTechnologyStageOperation
Haden2,000 MWSolar photovoltaicConstruction2026
Muwayh2,000 MWSolar photovoltaicConstruction2026
Alghat600 MWWindConstruction2026
Waad Al Shammal500 MWWindConstruction2026
Henakiyah 2400 MWSolar photovoltaicConstruction2026
Tabarjal400 MWSolar photovoltaicConstruction2026
Rabigh 2300 MWSolar photovoltaicConstruction2026
NGHC3,900 MWHybrid solar and wind plantsConstruction2027
Al Humaij3,000 MWSolar photovoltaicConstruction2027
Bisha3,000 MWSolar photovoltaicConstruction2027
Afif 22,000 MWSolar photovoltaicConstruction2027
As Sdawi2,000 MWSolar photovoltaicConstruction2027

Source: Renewable Vision, The Saudi Renewables Tracker, records compiled 2026-09-28. Map borders: Natural Earth, indicative.

Information, not advice. Built with RV Studio.