Saudi renewables: what comes next
3 projects are yet to operate, 2.0 GW in all: 1.4 GW under construction and 600 MW awarded, in tender or announced.
- Projects
- 3
- Tracked capacity
- 2.0GW3 projects
- Under construction
- 1.4GW2 projects
- Awarded, in tender or announced
- 600MW1 project
Capacity due by year of operation
1.4 GW2027
600 MW2029
Years are the sources’ own commercial operation dates, planned or actual, and move. Projects without a date are left out.
Where it is being built
- Under construction
- Awarded, in tender or announced
Circle area shows capacity. Locations are locality points, indicative, not surveyed sites.
Capacity to come by province
- Hail2.0 GW3 projects
Projects by year of operation
| Project | Capacity | Technology | Stage | Operation |
|---|---|---|---|---|
| Al Masa'a | 1,000 MW | Solar photovoltaic | Construction | 2027 |
| Sufun | 400 MW | Solar photovoltaic | Construction | 2027 |
| Mawqaq | 600 MW | Solar photovoltaic | Procurement | 2029 |