Saudi renewables: what comes next
7 projects are yet to operate, 13.3 GW in all: 6.3 GW under construction and 7.0 GW awarded, in tender or announced.
- Projects
- 7
- Tracked capacity
- 13.3GW7 projects
- Under construction
- 6.3GW4 projects
- Awarded, in tender or announced
- 7.0GW3 projects
Capacity due by year of operation
4.3 GW2026
2.0 GW2027
7.0 GW2029
Years are the sources’ own commercial operation dates, planned or actual, and move. Projects without a date are left out.
Where it is being built
- Under construction
- Awarded, in tender or announced
Circle area shows capacity. Locations are locality points, indicative, not surveyed sites.
Capacity to come by province
- Makkah13.3 GW7 projects
Projects by year of operation
| Project | Capacity | Technology | Stage | Operation |
|---|---|---|---|---|
| Haden | 2,000 MW | Solar photovoltaic | Construction | 2026 |
| Muwayh | 2,000 MW | Solar photovoltaic | Construction | 2026 |
| Rabigh 2 | 300 MW | Solar photovoltaic | Construction | 2026 |
| Khulis | 2,000 MW | Solar photovoltaic | Construction | 2027 |
| Al-Leeth | 3,000 MW | Solar photovoltaic | Procurement | 2029 |
| Muwayh 2 | 2,000 MW | Solar photovoltaic | Procurement | 2029 |
| Haden 2 | 2,000 MW | Solar photovoltaic | Procurement | 2029 |