Free report · Renewables investment and operations
How does SAR 30.87 billion of Saudi Arabia’s 15 GW round split by project?
October 2026 review. Five solar plants and two wind farms make up the SAR 30.87bn round, and wind carries the highest investment per MW. Earlier solar plants and three storage agreements take the wider project list to SAR 46.48bn.
The report
Saudi Arabia’s 15 GW round: how SAR 30.87 billion splits by project
What the report covers
- Gross investment of SAR 30.87bn across five solar plants (12 GW) and two wind farms (3 GW), at 30 September 2026.
- The five round PV plants average SAR 1.86m per MW; wind carries the highest investment per MW.
- Bisha and Al Humaj each combine 3 GW of solar with gross investment of about SAR 5.7bn; Starah has a similar budget for 2 GW of wind.
- Earlier solar plants and three storage agreements take the wider project list to SAR 46.48bn.
SAR 30.87bn
Gross investment across the seven generation projects of the 15 GW round at 30 September 2026.
Download the PDF (free, no sign-up) (PDF, opens in a new tab)
13 pages · in English · published 24 November 2026
Sources: ACWA project portfolio workbook, 30 September 2026 · Saudi Exchange (Tadawul) financial-close announcements · ACWA storage services agreements · LCGPA local content certificate
The PDF lists every source, with links and the dates they were retrieved.
Related reports
Renewables investment and operations
Who will run and maintain the 12 GW of Saudi solar coming into operation in 2027 and 2028?
October 2026 review. ACWA’s five solar plants reach full commercial operation in two waves of 6 GW, in Q4 2027 and Q1 2028. Fourteen grid-connected plants already account for 11.913 GW and need field support now.
Renewables investment and operations
How much capital does a gigawatt of Saudi solar take?
Reconcile installed capacity with the capital committed to five Saudi solar projects.
Grid storage
How much lithium-ion storage does Saudi Arabia import, and from where?
Lithium-ion imports nearly quadrupled in 2025, and China supplied 98.7% of them. Customs records cover every end use, so the report measures grid demand through the storage contracts and sets out how to compare bids on energy delivered at the meter.