- SAR 1,850/kW: weighted total project investment per contracted gross kW across five plants that reached financial close in November 2025.
- Bisha and Humaij, 3 GW each, at SAR 5.7bn each; Khulis, Afif 1 and Afif 2, 2 GW each, at SAR 3.6bn each.
- The two 3 GW projects are reported at about SAR 1,900/kW and the three 2 GW projects at about SAR 1,800/kW.
- Acwa names SPPC as procurer and off-taker, and Acwa, Badeel and SAPCO as co-owners: the electricity buyer is not the equipment buyer.
Download the PDF (free, no sign-up) (PDF, opens in a new tab)
7 pages · in English · published 24 November 2026
Sources: Acwa Q3 2026 investor report · Acwa financing announcement · Acwa 2025 board report
The PDF lists every source, with links and the dates they were retrieved.
Related reports
Renewables investment and operations
How does SAR 30.87 billion of Saudi Arabia’s 15 GW round split by project?
October 2026 review. Five solar plants and two wind farms make up the SAR 30.87bn round, and wind carries the highest investment per MW. Earlier solar plants and three storage agreements take the wider project list to SAR 46.48bn.
Renewables investment and operations
Who will run and maintain the 12 GW of Saudi solar coming into operation in 2027 and 2028?
October 2026 review. ACWA’s five solar plants reach full commercial operation in two waves of 6 GW, in Q4 2027 and Q1 2028. Fourteen grid-connected plants already account for 11.913 GW and need field support now.
Grid storage
How much lithium-ion storage does Saudi Arabia import, and from where?
Lithium-ion imports nearly quadrupled in 2025, and China supplied 98.7% of them. Customs records cover every end use, so the report measures grid demand through the storage contracts and sets out how to compare bids on energy delivered at the meter.