Saudi renewables at a glance
3 projects and 5.1 GW tracked: 3.0 GW under construction against 0 MW operating.
- Projects
- 3
- Tracked capacity
- 5.1GW3 projects
- Operating
- 0MW0 projects
- Under construction
- 3.0GW1 project
Capacity by stage
- Under construction3.0 GW1 project
- Awarded, in tender or announced2.1 GW2 projects
Where the projects are
- Under construction
- Awarded, in tender or announced
Circle area shows capacity. Locations are locality points, indicative, not surveyed sites.
Capacity by technology
- Solar photovoltaic3.6 GW2 projects
- Wind1.5 GW1 project
Capacity by province
- Aseer5.1 GW3 projects
Commercial operation by year
3.0 GW2027
2.1 GW2029
Years are the sources’ own commercial operation dates, planned or actual, and move. Projects without a date are left out.
The ten largest projects
| Project | Capacity | Technology | Stage | Place |
|---|---|---|---|---|
| Bisha | 3,000 MW | Solar photovoltaic | Construction | Aseer |
| Al Qirah | 1,500 MW | Wind | Procurement | Aseer |
| Tathleeth | 600 MW | Solar photovoltaic | Procurement | Aseer |